Conveyor retrofits that fit around the operation.

When an operating system needs to grow or change, the work has to fit around the building as it is today. ESCMAR installs expansions, line modifications and equipment upgrades — planned around existing equipment and the facility’s schedule.

EXISTING LINEEND STOPEXPANSION AREATIE-IN 01TIE-IN 02 · NEW DIVERTNEW SPUR

Showing the modified layout.

Fig. 01Existing line and modifications, plan — illustrative. Toggle to compare.
Service
03 — Retrofits & upgrades
Work types
Modify · expand · reconfigure · upgrade
Method
Phased installation
Facilities
Operating sites

01What a retrofit involves

Changing a system that is already running.

A retrofit changes an existing conveyor system: extending a line, adding a merge or divert, rerouting conveyor around a new process, or replacing worn or outdated components. Unlike a new installation, the work ties into equipment that is already in use — so the planning question isn’t only what to install, but when, in what order, and with how much downtime.

New installation vs. retrofit
Starting pointEmpty floor and new drawingsAn existing system and its real condition
ConstraintDelivery and trade scheduleOperation, downtime windows, live equipment
Critical stepLayout and alignmentField verification and tie-ins

02Types of retrofit work

Four kinds of change.

Retrofit and upgrade work installed to the design of the integrator or equipment manufacturer — ESCMAR provides the mechanical installation.
01

Existing-system modifications

Cutting in new sections, relocating conveyor, adding transfers, or changing elevations so the line suits new equipment or a new process.

02

Capacity expansion

Line extensions, added lanes, accumulation and new spurs that let an existing system handle more volume — installed to the integrator’s expansion design.

03

Line reconfiguration

Rerouting conveyor for a new layout, process area or product flow, reusing existing equipment where the design allows it.

04

Component upgrades

Replacing drives, rollers, belts, guarding and other components with new or upgraded equipment, matched to the existing system as specified.

03Phased installation & shutdown coordination

Most of the work happens before the shutdown.

When a tie-in needs the line stopped, the window is short and fixed. Everything that can be done beforehand is — so the window is spent only on what has to happen inside it.
  1. 01

    Before the window

    • Walk every tie-in point with the facility team
    • Pre-assemble new sections off-line where possible
    • Stage materials and tools at the point of use
    • Confirm lockout, permits and access with the facility
  2. 02

    During the window

    • Remove or cut existing equipment as planned
    • Tie in new sections and transfers
    • Check alignment and elevations at each new transfer
    • Keep scope to what can finish inside the window
  3. 03

    After the window

    • Reinstall guarding before restart
    • Support restart and testing by the facility and integrator
    • Work the punch list
    • Plan the next phase from what was learned

04Compatibility & risk

Questions worth answering before a retrofit starts.

Most retrofit surprises come from assumptions about the existing system. These are the questions that remove them — answered by the facility, the integrator or manufacturer, and the installation team together.

  1. 01Have existing elevations, widths and dimensions been field-verified — not just taken from old drawings?
  2. 02Are new and existing components compatible (frame profiles, roller centres, widths, drive arrangements)? The manufacturer or integrator confirms this.
  3. 03Is the existing equipment at each tie-in in a condition to accept the new work?
  4. 04Which areas stay live, and where are the boundaries and exclusion zones?
  5. 05What happens if a tie-in can’t be completed inside its window — is there a rollback plan?
  6. 06Who records the as-built changes so the next modification starts from accurate drawings?

06FAQ

Retrofit and upgrade questions.

Something specific about your project? Email info@escmarconveyors.com.

  • In most cases, yes — that is what phasing is for. ESCMAR’s teams are experienced in active distribution environments; work is split into separated areas and agreed windows so the operation keeps running around it.

  • Yes. Retrofit work starts from the system as it exists today, whoever installed it. Field verification of the existing equipment comes first, and component compatibility is confirmed with the manufacturer or integrator.

  • By doing as much as possible before the shutdown window — verifying dimensions, pre-assembling and staging — so the window itself is spent on tie-ins only. The window schedule is agreed with the facility in advance.

  • Line modifications and reconfiguration — including relocating and reusing existing equipment where the design allows — are part of retrofit and upgrade work. Describe the change in your quote request and the team will follow up.

Request a quote

Planning an expansion or modification?

Describe the existing system and what needs to change. ESCMAR will follow up on phasing, windows and crew requirements.

Helpful to include

  • 01Existing system and manufacturer
  • 02What needs to change
  • 03Operating hours and possible shutdown windows
  • 04Existing and proposed layout drawings
  • 05Target completion