Installation service 03
Conveyor retrofits that fit around the operation.
When an operating system needs to grow or change, the work has to fit around the building as it is today. ESCMAR installs expansions, line modifications and equipment upgrades — planned around existing equipment and the facility’s schedule.
Showing the modified layout.
- Service
- 03 — Retrofits & upgrades
- Work types
- Modify · expand · reconfigure · upgrade
- Method
- Phased installation
- Facilities
- Operating sites
01What a retrofit involves
Changing a system that is already running.
A retrofit changes an existing conveyor system: extending a line, adding a merge or divert, rerouting conveyor around a new process, or replacing worn or outdated components. Unlike a new installation, the work ties into equipment that is already in use — so the planning question isn’t only what to install, but when, in what order, and with how much downtime.
| Starting point | Empty floor and new drawings | An existing system and its real condition |
|---|---|---|
| Constraint | Delivery and trade schedule | Operation, downtime windows, live equipment |
| Critical step | Layout and alignment | Field verification and tie-ins |
02Types of retrofit work
Four kinds of change.
Existing-system modifications
Cutting in new sections, relocating conveyor, adding transfers, or changing elevations so the line suits new equipment or a new process.
Capacity expansion
Line extensions, added lanes, accumulation and new spurs that let an existing system handle more volume — installed to the integrator’s expansion design.
Line reconfiguration
Rerouting conveyor for a new layout, process area or product flow, reusing existing equipment where the design allows it.
Component upgrades
Replacing drives, rollers, belts, guarding and other components with new or upgraded equipment, matched to the existing system as specified.
03Phased installation & shutdown coordination
Most of the work happens before the shutdown.
01
Before the window
- Walk every tie-in point with the facility team
- Pre-assemble new sections off-line where possible
- Stage materials and tools at the point of use
- Confirm lockout, permits and access with the facility
02
During the window
- Remove or cut existing equipment as planned
- Tie in new sections and transfers
- Check alignment and elevations at each new transfer
- Keep scope to what can finish inside the window
03
After the window
- Reinstall guarding before restart
- Support restart and testing by the facility and integrator
- Work the punch list
- Plan the next phase from what was learned
04Compatibility & risk
Questions worth answering before a retrofit starts.
Most retrofit surprises come from assumptions about the existing system. These are the questions that remove them — answered by the facility, the integrator or manufacturer, and the installation team together.
- 01Have existing elevations, widths and dimensions been field-verified — not just taken from old drawings?
- 02Are new and existing components compatible (frame profiles, roller centres, widths, drive arrangements)? The manufacturer or integrator confirms this.
- 03Is the existing equipment at each tie-in in a condition to accept the new work?
- 04Which areas stay live, and where are the boundaries and exclusion zones?
- 05What happens if a tie-in can’t be completed inside its window — is there a rollback plan?
- 06Who records the as-built changes so the next modification starts from accurate drawings?
05Related
Industries and services.
Industries
- 05ManufacturingMechanical conveyor installation for production lines, packaging operations, finished-goods handling, and facility automation.
- 02Retail & E-CommerceConveyor installation for retail distribution centers, fulfillment operations, apparel facilities, and e-commerce networks.
- 03Beverage & Liquor DistributionConveyor installation for beverage warehouses, liquor distribution centers, and case-handling operations.
- 04Healthcare & PharmaceuticalMechanical installation support for pharmacy automation, central-fill systems, medical-product distribution, and healthcare warehouse operations.
Services
- 01Conveyor System InstallationComplete mechanical installation support for distribution and fulfillment operations.
- 02Sortation System InstallationExperience with high-throughput sortation environments and active facilities.
- 04Project Recovery SupportAdditional installation capacity for projects operating under compressed timelines.
06FAQ
Retrofit and upgrade questions.
Something specific about your project? Email info@escmarconveyors.com.
In most cases, yes — that is what phasing is for. ESCMAR’s teams are experienced in active distribution environments; work is split into separated areas and agreed windows so the operation keeps running around it.
Yes. Retrofit work starts from the system as it exists today, whoever installed it. Field verification of the existing equipment comes first, and component compatibility is confirmed with the manufacturer or integrator.
By doing as much as possible before the shutdown window — verifying dimensions, pre-assembling and staging — so the window itself is spent on tie-ins only. The window schedule is agreed with the facility in advance.
Line modifications and reconfiguration — including relocating and reusing existing equipment where the design allows — are part of retrofit and upgrade work. Describe the change in your quote request and the team will follow up.
Request a quote
Planning an expansion or modification?
Describe the existing system and what needs to change. ESCMAR will follow up on phasing, windows and crew requirements.
Helpful to include
- 01Existing system and manufacturer
- 02What needs to change
- 03Operating hours and possible shutdown windows
- 04Existing and proposed layout drawings