Key points
- Design, supply, installation, electrical and commissioning are usually separate scopes.
- The interfaces — anchors, lifts, guarding, device mounting — are where gaps appear.
- Drawings, revisions and questions (RFIs) need one controlled path.
- Installers support commissioning; they don’t replace it.
The roles
Conveyor projects bring together companies that each specialise in one part of the job. Titles vary by project, but the division of labor is consistent:
- Equipment manufacturer (OEM) — designs and builds the conveyor, sortation or other equipment, and publishes its installation requirements.
- System integrator — designs the overall system, often from several manufacturers’ equipment, and normally delivers controls, software and commissioning. On some projects the OEM is also the integrator.
- Mechanical installation contractor — installs the equipment on site to the approved drawings and the manufacturer’s requirements.
- Electrical contractor — installs power, wiring and devices, and terminates motors and panels.
- General contractor — controls the site and coordinates the building trades.
- Owner and facility team — define the requirements, set the schedule and site rules, and operate the result.
Where the scopes meet
Each interface between two scopes is a place where something can be done twice or not at all. The common ones on conveyor projects are:
- Deliveries — who receives, unloads, inspects and stages equipment.
- Anchoring and structure — who supplies anchors, and who provides support steel for hung or mezzanine conveyor.
- Access equipment — who provides and pays for aerial lifts and forklifts.
- Devices — photo-eyes, motors and controls hardware are often mounted mechanically by one party and wired by another.
- Guarding — what is supplied with the equipment and what is field-installed or field-fabricated.
- Field changes — who approves a modification when the site doesn’t match the drawing.
- Debris and cleanup — who removes packaging and dunnage, and where it goes.
Information flow
The installation team works from the integrator’s or OEM’s drawings, so drawing control matters. Revisions should be issued through one channel and the field should be able to confirm it is on the latest set. Questions from the field — requests for information — should go to the designer in writing, with an answer recorded before the work proceeds. A brief daily coordination between installation, the integrator and the GC keeps deliveries, work areas and lift use aligned.
Scope boundaries worth writing down
Most disputes on conveyor projects are not about quality; they are about who was supposed to do something. Before work starts, it is worth agreeing in writing:
- Unloading and staging responsibilities.
- Lifts and site equipment — who provides, who pays.
- Anchors, support steel and any field-fabricated parts.
- Device mounting versus wiring.
- Guarding supplied versus field-installed.
- Support expected from installation during testing and commissioning.
- How field changes and extra work are approved.
During commissioning
Commissioning belongs to the integrator, but the system it is testing was built by the installation team, and mechanical adjustments are common in the first days of operation — belt tracking, transfer alignment, guide settings. Agreeing in advance how much installation support is available during testing, and for how long, avoids a gap at exactly the moment the project is closest to the finish.
What good coordination looks like
- One controlled drawing set and a written RFI process.
- A written scope split that covers the interfaces above.
- Deliveries sequenced to the install plan.
- Short daily coordination between installation, integrator and GC.
- Mechanical completion handed over area by area, ready for the next trade.
How ESCMAR fits
ESCMAR is a mechanical installation contractor. It works closely with general contractors, engineers, equipment manufacturers and facility teams to complete installations according to project specifications, and supports leading industry partners on high-volume projects. See ESCMAR’s services.
References
- ASME B20.1 — Safety Standard for Conveyors and Related Equipment (opens in a new tab)
The U.S. consensus safety standard covering conveyor design, construction, installation, maintenance, inspection and operation (current edition 2024).
Standards are referenced for context only — consult the current edition and your project’s specifications. ESCMAR does not claim certification to any standard listed.